June 2022. HAVIERON
14/05/21. Decline commences. (460m deep / 3km long).
15/07/21. Mine officially open.
Q4/21. Growth drilling continues. 40,000m (Dec ‘21 to Jun ‘22 inc).
02/22. 5% valuation initial agreement date. No expiry date.
03/03/22. GGP MRE2 published. [5.5mozAu / 218ktCu: 6.5mozAuEq].
08/07/22. Bromus mining rights expire.
20/07/22. NCM June quarterly results. 6 assays pending. [BST].
21/07/22. GGP 6 weekly update?
18/08/22. NCM Full year results. MR&OR update up to 30/6. (NCM mre2?) [BST].
01/09/22. GGP 6 weekly update?
09/22. GDXJ rebalance.
13/10/22. GGP 6 weekly update?
10/22. Byrnecut contract for first decline terminates.
26/10/22. NCM quarterly results. [BST].
02/11/22. GGP Annual Report. (KPI’s for SD’s 12m share option).
11/22. Sprott ETF review of GGP.
24/11/22. GGP 6 weekly update?
12/22. GDXJ rebalance
Q4/22. D.F.S. Decision to Bulk Mine (as a JV) by NCM / GGP.*
[NCM loan of $50m runs out on completion of DFS].
Q4/22. Bulk Mine decline commences. [750m+ deep / 6km long].
01/11/23. Panorama mining rights expire.
2023. Drilling commences @ Ernest Giles.
Q4/23. Exploration decline and ventilation shafts complete.
H2FY24. (01/24 to 06/24 inc). SLOS first Ore. First cash flow.
Q2/24. Sub Level Open Stoping (SLOS) construction commences.
Q2/24. First bulk production of Gold/Copper.
[Est production profile over 12 yrs: 25mt@3.4gAu/t / 0.44%cu]
[2.4MozAu/109ktCu].
Q3/26. 2 x Bulk Underground Mine construction (E Breccia and N Breccia?) begins.
2028. BUM production. Operating in tandem with SLOS.
2036. SLOS estimated end of life based on: (4.2MozAuEq / 3Mt/yr / 12 years).
2053+. BUM estimated end of life.

* If there is a decision to mine as a JV @ the DFS or the 5% FMV is agreed
(whichever is first), it will result in payment of 145m shares to Pacific Trends
Resources
DipSard
The Oracle
The Oracle
Reactions:
Posts: 247
Joined: Fri Jun 17, 2022 5:12 pm
Contact:

Re: June RoadMap

Post by DipSard »

It would be great to have an area for your roadmaps akin to what Liam's done for my interview notes zoros

Liam - could you perhaps just use a link to a Zoros roadmap section of the forum on GGPhelp.co.uk?

That way, no need for you/Zoros to update the GGPHelp site - a web site visitor just follows a link to the Zoros roadmap sticky on GGPChat and opens up the latest roadmap entry, over time we will also have a historical list as Zoros makes new entries....
“Study the past if you would define the future.” ― Confucius
User avatar
Bottle Rocket - Liam
DEV TEAM
DEV TEAM
Reactions:
Posts: 336
Joined: Wed Jun 01, 2022 10:43 pm
Location: Somewhere
Contact:

Re: June RoadMap

Post by Bottle Rocket - Liam »

Zoros this has now been completed, Not sure if where i have put it is where it will stay, but for now, this is the plan, I want to try and keep the board as clutter free as possible.

Liam
Liam.
"One mine, three mining areas, a BEAST of an ore body" :!:
Locked