ROADMAP
Posted: Thu Jan 26, 2023 12:00 am
Modified 24 September 2024
14/05/21. Decline commences. (460m deep / 2800m long).
15/07/21. Mine officially started.
03/03/22.GGP MRE2 [5.5mozAu / 218ktCu: 6.5mozAuEq].
05/23. Farm in with Rio Tinto @ Paterson South. $7m exploration costs by 2030. $21m by 2033. (Stingray and Decka).
21/12/23. GGP MRE(3) [7.04mozAu / 275ktCu: 8.4mozAuEq]. https://www.youtube.com/watch?v=lE9ly_RF7mk
02/24 Inventum 3D video: https://inventum3d.com/c/greatlandgold/havieron.
11/23. Decline halted ( dewatering lower aquifer).
10/09/24. Reverse acquisition of NEM @ Tel/Hav,
30/09/24. 5.3Bn share issue (equity raise for acquisition). 10.1bn in total.
12/24. Tel/Hav acquisition complete.
H2/24. Further exploration Ernest Giles.
Q4/24. Telfer resumes production (12-18 months lifex. 450+koz stockpiled.). Telfer has priority over Hav..
Q1/25. GGP ASX300 listing.
Q1/25. Telfer MRE.
Q2/25. Telfer Reserve update.
Q2/25. FS Hav.
H2/25. Hav decline re-starts. DFS due (KPI: within 12 months of Telfer acquisition).
09/09/25. Co-invested Options (held by ‘new directors’ 9/22), tradeable.
Q1/26. KPI: Debt financing in place to complete Hav development.
H2/26. Development Ore (stockpiling) @ Hav.
H1/27. First Gold @ Hav. (FCF@Hav).
2028. B.U.M production. Operating in tandem with SLOS.
2042. SLOS estimated end of life based on: (4.2MozAuEq / 2.8Mt/yr / 12 years).
(To be amended at DFS.)
2053+ B.U.M estimated end of life
Z
14/05/21. Decline commences. (460m deep / 2800m long).
15/07/21. Mine officially started.
03/03/22.GGP MRE2 [5.5mozAu / 218ktCu: 6.5mozAuEq].
05/23. Farm in with Rio Tinto @ Paterson South. $7m exploration costs by 2030. $21m by 2033. (Stingray and Decka).
21/12/23. GGP MRE(3) [7.04mozAu / 275ktCu: 8.4mozAuEq]. https://www.youtube.com/watch?v=lE9ly_RF7mk
02/24 Inventum 3D video: https://inventum3d.com/c/greatlandgold/havieron.
11/23. Decline halted ( dewatering lower aquifer).
10/09/24. Reverse acquisition of NEM @ Tel/Hav,
30/09/24. 5.3Bn share issue (equity raise for acquisition). 10.1bn in total.
12/24. Tel/Hav acquisition complete.
H2/24. Further exploration Ernest Giles.
Q4/24. Telfer resumes production (12-18 months lifex. 450+koz stockpiled.). Telfer has priority over Hav..
Q1/25. GGP ASX300 listing.
Q1/25. Telfer MRE.
Q2/25. Telfer Reserve update.
Q2/25. FS Hav.
H2/25. Hav decline re-starts. DFS due (KPI: within 12 months of Telfer acquisition).
09/09/25. Co-invested Options (held by ‘new directors’ 9/22), tradeable.
Q1/26. KPI: Debt financing in place to complete Hav development.
H2/26. Development Ore (stockpiling) @ Hav.
H1/27. First Gold @ Hav. (FCF@Hav).
2028. B.U.M production. Operating in tandem with SLOS.
2042. SLOS estimated end of life based on: (4.2MozAuEq / 2.8Mt/yr / 12 years).
(To be amended at DFS.)
2053+ B.U.M estimated end of life