Haul Road

Mine, and decline specific questions - Opens in July
Francis
Reactions:
Posts: 36
Joined: Thu Jul 21, 2022 3:00 am

Haul Road

Post by Francis »

A question for this boards resident experts. What is the status of the haul road required between Hav and Telfer? Is it being built already as part of the pre-mining works? If not, when will work on it start and how long might it take?
Hydrogen
Reactions:
Posts: 559
Joined: Sun Jun 26, 2022 11:24 am

Re: Haul Road

Post by Hydrogen »

Hi Francis.

There were some info on LinkedIn recently with a contractor talking about delivery of a 32km Widening contract of the Havieron access road and something earth works associated with the evaporation ponds.


https://www.linkedin.com/feed/update/ur ... 1554304%29
In the end, Truth prevails...
Bamps21
Reactions:
Posts: 752
Joined: Sun Jun 26, 2022 9:41 am

Re: Haul Road

Post by Bamps21 »

90346004-fb5e-4b04-95b4-08b215917474.jpeg
796899e2-5633-42e3-9b97-912d1df21105.jpeg
These were from the latest revisions submitted recently.
From the satellites it doesn’t look as though it’s been completed yet.
Bamps21
Reactions:
Posts: 752
Joined: Sun Jun 26, 2022 9:41 am

Re: Haul Road

Post by Bamps21 »

IMG_6112.jpeg
IMG_6113.jpeg
IMG_6114.jpeg
Looks like the main construction work can’t start until the EPA approval for Stage 2
At the moment there’s 2 roads from Havieron running alongside each other up to the new junction position.
From there it’s just one road the Northern access road which is what’s in that LinkedIn photo
Francis
Reactions:
Posts: 36
Joined: Thu Jul 21, 2022 3:00 am

Re: Haul Road

Post by Francis »

Bamps21 wrote: Tue Dec 19, 2023 4:03 pm Looks like the main construction work can’t start until the EPA approval for Stage 2
Once EPA approval for Stage 2 is in place, how long will it take to build the 55km haul road between Havieron and Telfer?
User avatar
strudel
Reactions:
Posts: 105
Joined: Sun Jun 26, 2022 2:34 pm

Re: Haul Road

Post by strudel »

Less time than it takes to drill through the last 80m of vertical decline.....

In project speak the road isn't on the "critical path".

You can have multiple crews working simultaneously all along the 55km length if you want to shorten time lines.
Read on, the next poster will cover it all better....