A question for this boards resident experts. What is the status of the haul road required between Hav and Telfer? Is it being built already as part of the pre-mining works? If not, when will work on it start and how long might it take?
Re: Haul Road
Hi Francis.
There were some info on LinkedIn recently with a contractor talking about delivery of a 32km Widening contract of the Havieron access road and something earth works associated with the evaporation ponds.
https://www.linkedin.com/feed/update/ur ... 1554304%29
There were some info on LinkedIn recently with a contractor talking about delivery of a 32km Widening contract of the Havieron access road and something earth works associated with the evaporation ponds.
https://www.linkedin.com/feed/update/ur ... 1554304%29
In the end, Truth prevails...
Re: Haul Road
From the satellites it doesn’t look as though it’s been completed yet.
Re: Haul Road
At the moment there’s 2 roads from Havieron running alongside each other up to the new junction position.
From there it’s just one road the Northern access road which is what’s in that LinkedIn photo
Re: Haul Road
Less time than it takes to drill through the last 80m of vertical decline.....
In project speak the road isn't on the "critical path".
You can have multiple crews working simultaneously all along the 55km length if you want to shorten time lines.
In project speak the road isn't on the "critical path".
You can have multiple crews working simultaneously all along the 55km length if you want to shorten time lines.
Read on, the next poster will cover it all better....